Longford Park Primary School - New Longford Park Primary School

Banbury, Oxfordshire
Client : Longford Park Primary School
Architect : Capita
Completion : October 2016
Project Value: £5 million

The brief

Sabin Consulting Engineers Ltd were appointed to work with Capita Architects and Structural Engineers as part of the design team for the new Longford Park Primary School.

The project involved the construction of a new primary school located on the new Longford Park residential development in Banbury. The new school was constructed by Carillion with Imtech Engineering Services installing the M&E services and was completed in October 2016.

The solution

The services strategy includes the utilisation of high efficiency condensing gas boilers with variable speed pumping installations, a comprehensive natural ventilation strategy including night cooling, LED lighting installations and PV solar.